Overview
The City of Roseville manages a comprehensive Pavement Management Program (PMP) which includes repaving several miles of local streets annually. In 1986, Roseville began a program to reconstruct substandard residential streets. The PMP upgrades streets by neighborhood based on street condition.
To see which streets are scheduled to be repaved and have utility work done this summer, please see the 2023 Proposed PMP Project Map. Note that road segments have been removed from the original scope and may be further reduced based on project costs.
The majority of the roadways will have the top two inches of pavement removed and repaved. In addition to the street resurfacing work, some spot curb and gutter will be replaced. All curb ramps for pathways will be upgraded to meet ADA compliance. Minor utility repairs in the area will be performed with this project including sanitary sewer, water and storm sewer.
The cost of this project is funded by existing City funds. There will be NO ASSESSMENTS for this work within the City of Roseville.
Schedule
Winter 2023 – Project Design
March 15, 2023 – Deadline to Notify City of Sanitary Sewer Service Repair/Replacement Coordination
April 2023 – Bidding
May 2023 – City Council Accept Bids and Award Contract
Summer 2023 – Construction