Overview


The City of Roseville manages a comprehensive Pavement Management Program which includes repaving several miles of local streets annually.  In 1986 Roseville began a program to reconstruct substandard residential streets. This program, called the Pavement Management Program (PMP), upgrades streets by neighborhood based on street condition.

In 2017, the City is planning to mill and overlay about eight miles of streets.  To see which streets are being repaved this summer please see the
2017 Project Map.  
The majority of the roadways will have the top two inches of pavement milled off, or removed, and repaved.

The cost of this project is funded by existing City funds. There will be NO ASSESSMENTS for this work within the City of Roseville.

Project Schedule


Week of July 24
  • Watermain replacement: Gluek Lane
  • Bituminous and Curb removal on Fernwood street
  • Storm Sewer Replacement on Fernwood Street
Week of July 31
  • Milling:  Ryan Avenue (Fernwood Street to Lexington Avenue), Belmont Lane, Commerce Street, Albert Street
  • Curb Replacement:  Ryan Avenue (Fernwood Street to Lexington Avenue), Belmont Lane, Commerce Street, Albert Street
  • Watermain replacement:  Gluek Lane
Week of August 7
  • Paving:  Ryan Avenue (Fernwood Street to Lexington Avenue), Belmont Lane, Commerce Street, Albert Street
  • Restoration: Ryan Avenue (Fernwood Street to Lexington Avenue), Belmont Lane, Commerce Street, Albert Street
  • Watermain replacement: Eldridge Avenue